Year 2013
Projects

2013 Projects

AMX-1 F.O Cable System BRAZIL Seg.1.6 & Seg.3.1 for Alcatel-Lucent.

Project involved the Direct Shore End Landings of Fiber Optic Cables to two landing sites (Praia do Futuro I & II) in Fortaleza, Brazil including installation of Articulated Pipes (200m each) Cable Protection Systems, Offshore Cable Burial to 1m target burial depth, diver inshore surveys and installation of Ocean Ground Beds.

All project equipment and spreads were locally fabricated, tested and deployed with preparations undertaken by Maritech’s Engineering & Design department and fabrications supervised by Maritech’s Technicians & Chief Engineers. Implications due to importation restraints were effectively avoided and project was executed safely, effectively and on-time.

AMX-1 F.O Cable System GUATEMALA Seg.4.4 for Alcatel-Lucent.

Project involved the Mobilisation of Maritech’s Shallow Draft, Installation & Repair Vessel, the C/S Ikaros, fully loaded with all survey, installation & protection spreads, Mobilised from Piraeus, Greece to Guatemala.

Cable Loading was completed in Curacao and followed by the installation of a 25km Pre-laid Shore End Landing in the territorial waters of Puerto Barrios, Guatemala including installation of Articulated Pipes (100m) Cable Protection Systems, Offshore Cable Burial to 2m target burial depth using the SKAS IV Cable Trencher.

All operations were completed successfully, on-time & on-budget via our turnkey approach eliminating many of the local particularities for our client.

POSEIDON Survey & HDD Installation for Ocean Specialists Inc.

Project involved the Geophysical and Geotechnical Land and inshore survey works including Bathymetry,Core sampling using a Jack-Up Platform, Burial Assessment Study, Morphological Seafloor Mapping and detailed drawings to two landing sites of Pentaskhinos & Yeroskipos in Cyprus.

Following the Geotechnical & Geophysical Surveys, 2 x  300m 4”D HDPE pipe Horizontal Directional Drilling installation works will be completed for the POSEIDON Cable System in both landing sites (Pentaskhinos & Yeroskipos) in Cyprus.

POSEIDON Deep Water Survey for TESubCom.

Project Involves an Offshore Deep Waters Marine Survey up to approx.3000m Water Depth. in Cypriot and Israeli territorial waters for POSEIDON Cable System route optimization.

Maritech is utilizing its own Survey Team & Survey Vessel fully outfitted with all survey equipment required to 3000m Water Depth to undertake the works in a turn-key fashion.

BERMUDA Cable System Survey & Installation for Quantum Communications.

Project involves the route survey using Maritechs Survey Team equipped with Side Scan Sonars and accompanied by Maritech’s Dive Team for a Diver Swim Survey along the cable route to allow route optimization.

Further, the Recovery and scrappage of an old redundant FO Cable will also be undertaken prior to the Pre-Laid Shore End Landing Installation operation of 3.7kms from Tucker’s Town to Southside, Bermuda.

Services provided include the Supply & Installation of Articulated Pipes (250m) Cable Protection Systems, 225 Concrete Bags and 360 Steel Pins to protect the cable throughout the rocky / coral seabeds without interfering with the protected areas via trenching.

MARITECH News

PCCS F.O. Cable System Aruba Seg. 3

Project involved the Direct Shore End Landing through 520m pre-installed duct of Fiber Optic Cable to one landing site (Arashi), Aruba including diver inshore surveys and installation of Articulated Pipes (25m) Cable Protection Systems.
All project equipment and spreads were locally fabricated, tested and deployed with preparations undertaken by Maritech’s personnel. Project was executed safely, effectively and on-time.


2014-A-PCCS-RW-USA

Maritech performed remedial protection works for Alcatel-Lucent, on the PCCS Submarine Fiber optic cable system at Segment 1 Jacksonville shore end. Remedial works included survey using RD-7000 Cable Tracker, articulated pipe installation and re-burial of cable within a challenging surf zone.
Works have been successfully completed in a timely and safely manner.


2014-A-PCCS-USA

Maritech successfully completed a 3km Direct Shore end including Burial with its subsea SKAS Jet Trencher for the new Fiber Optic Cable PCCS connecting USA to the Caribbean. Water depths ranged from 0 to 25m with strong surf zones encountered however works were completed successfully in Jacksonville, Florida.

Maritech employed its US Subsidiary, Marpro LLC for these works.


2014-A-AMX1_RW-DR

Maritech successfully completed the remedial protection works of the AMX-1 Cable System in the Challenging surf zone of Fortaleza, Brazil. The particular cable system has been prone to exposures due to migrating sediments on the seabed caused by strong surf and current conditions. This led to the Subsea Cable being left un- protected to external threat following its initial burial. Maritech successfully mitigated this threat employing its Dive Supervisors with a Maritech Local Dive Team and Spreads permanently imported in Brazil, to successfully install Articulated Pipes and Rock Clamps to the exposed cable in water depths up to 20m.


2014-T-SCILLY-UK

Maritech successfully completed a complicated 1.5km Direct Shore end including installation of mechanical protection and burial for the Scilly Islands Cable system connecting these remote islands to the UK with a re-cycled Fiber Optic Cable. This complicated project involved first recovering an Out Of Use Cable from the seabed and then relaying it from the UK to the Scilly Islands through a series of reefs and rock outcrops. Many anchoring points and careful planning of pull-in practices were employed to ensure the cable weaved through numerous rock outcrops and ensure it laid within sediment able to bury and protect the cable. Water depths ranged from 0 to 25m and works were completed successfully in St. Mary’s Island, Scilly, UK.
Maritech employed its UK Subsidiary for these works, Maritech UK Ltd while simultaneously working on the Scottish Highlands and Islands projects involving over 40 direct Shore End Subsea Cable Installations in only 3 months over the summer seasson of 2014.


PCCS F.O. Cable System Aruba Seg. 3

Project involved the Direct Shore End Landing through 520m pre-installed duct of Fiber Optic Cable to one landing site (Arashi), Aruba including diver inshore surveys and installation of Articulated Pipes (25m) Cable Protection Systems.
All project equipment and spreads were locally fabricated, tested and deployed with preparations undertaken by Maritech’s personnel. Project was executed safely, effectively and on-time.


2014-A-PCCS-RW-USA

Maritech performed remedial protection works for Alcatel-Lucent, on the PCCS Submarine Fiber optic cable system at Segment 1 Jacksonville shore end. Remedial works included survey using RD-7000 Cable Tracker, articulated pipe installation and re-burial of cable within a challenging surf zone.
Works have been successfully completed in a timely and safely manner.


2014-A-PCCS-USA

Maritech successfully completed a 3km Direct Shore end including Burial with its subsea SKAS Jet Trencher for the new Fiber Optic Cable PCCS connecting USA to the Caribbean. Water depths ranged from 0 to 25m with strong surf zones encountered however works were completed successfully in Jacksonville, Florida.

Maritech employed its US Subsidiary, Marpro LLC for these works.


2014-A-AMX1_RW-DR

Maritech successfully completed the remedial protection works of the AMX-1 Cable System in the Challenging surf zone of Fortaleza, Brazil. The particular cable system has been prone to exposures due to migrating sediments on the seabed caused by strong surf and current conditions. This led to the Subsea Cable being left un- protected to external threat following its initial burial. Maritech successfully mitigated this threat employing its Dive Supervisors with a Maritech Local Dive Team and Spreads permanently imported in Brazil, to successfully install Articulated Pipes and Rock Clamps to the exposed cable in water depths up to 20m.


2014-T-SCILLY-UK

Maritech successfully completed a complicated 1.5km Direct Shore end including installation of mechanical protection and burial for the Scilly Islands Cable system connecting these remote islands to the UK with a re-cycled Fiber Optic Cable. This complicated project involved first recovering an Out Of Use Cable from the seabed and then relaying it from the UK to the Scilly Islands through a series of reefs and rock outcrops. Many anchoring points and careful planning of pull-in practices were employed to ensure the cable weaved through numerous rock outcrops and ensure it laid within sediment able to bury and protect the cable. Water depths ranged from 0 to 25m and works were completed successfully in St. Mary’s Island, Scilly, UK.
Maritech employed its UK Subsidiary for these works, Maritech UK Ltd while simultaneously working on the Scottish Highlands and Islands projects involving over 40 direct Shore End Subsea Cable Installations in only 3 months over the summer seasson of 2014.


PCCS F.O. Cable System Aruba Seg. 3

Project involved the Direct Shore End Landing through 520m pre-installed duct of Fiber Optic Cable to one landing site (Arashi), Aruba including diver inshore surveys and installation of Articulated Pipes (25m) Cable Protection Systems.
All project equipment and spreads were locally fabricated, tested and deployed with preparations undertaken by Maritech’s personnel. Project was executed safely, effectively and on-time.


2014-A-PCCS-RW-USA

Maritech performed remedial protection works for Alcatel-Lucent, on the PCCS Submarine Fiber optic cable system at Segment 1 Jacksonville shore end. Remedial works included survey using RD-7000 Cable Tracker, articulated pipe installation and re-burial of cable within a challenging surf zone.
Works have been successfully completed in a timely and safely manner.


2014-A-PCCS-USA

Maritech successfully completed a 3km Direct Shore end including Burial with its subsea SKAS Jet Trencher for the new Fiber Optic Cable PCCS connecting USA to the Caribbean. Water depths ranged from 0 to 25m with strong surf zones encountered however works were completed successfully in Jacksonville, Florida.

Maritech employed its US Subsidiary, Marpro LLC for these works.


2014-A-AMX1_RW-DR

Maritech successfully completed the remedial protection works of the AMX-1 Cable System in the Challenging surf zone of Fortaleza, Brazil. The particular cable system has been prone to exposures due to migrating sediments on the seabed caused by strong surf and current conditions. This led to the Subsea Cable being left un- protected to external threat following its initial burial. Maritech successfully mitigated this threat employing its Dive Supervisors with a Maritech Local Dive Team and Spreads permanently imported in Brazil, to successfully install Articulated Pipes and Rock Clamps to the exposed cable in water depths up to 20m.


2014-T-SCILLY-UK

Maritech successfully completed a complicated 1.5km Direct Shore end including installation of mechanical protection and burial for the Scilly Islands Cable system connecting these remote islands to the UK with a re-cycled Fiber Optic Cable. This complicated project involved first recovering an Out Of Use Cable from the seabed and then relaying it from the UK to the Scilly Islands through a series of reefs and rock outcrops. Many anchoring points and careful planning of pull-in practices were employed to ensure the cable weaved through numerous rock outcrops and ensure it laid within sediment able to bury and protect the cable. Water depths ranged from 0 to 25m and works were completed successfully in St. Mary’s Island, Scilly, UK.
Maritech employed its UK Subsidiary for these works, Maritech UK Ltd while simultaneously working on the Scottish Highlands and Islands projects involving over 40 direct Shore End Subsea Cable Installations in only 3 months over the summer seasson of 2014.


PCCS F.O. Cable System Aruba Seg. 3

Project involved the Direct Shore End Landing through 520m pre-installed duct of Fiber Optic Cable to one landing site (Arashi), Aruba including diver inshore surveys and installation of Articulated Pipes (25m) Cable Protection Systems.
All project equipment and spreads were locally fabricated, tested and deployed with preparations undertaken by Maritech’s personnel. Project was executed safely, effectively and on-time.


2014-A-PCCS-RW-USA

Maritech performed remedial protection works for Alcatel-Lucent, on the PCCS Submarine Fiber optic cable system at Segment 1 Jacksonville shore end. Remedial works included survey using RD-7000 Cable Tracker, articulated pipe installation and re-burial of cable within a challenging surf zone.
Works have been successfully completed in a timely and safely manner.


2014-A-PCCS-USA

Maritech successfully completed a 3km Direct Shore end including Burial with its subsea SKAS Jet Trencher for the new Fiber Optic Cable PCCS connecting USA to the Caribbean. Water depths ranged from 0 to 25m with strong surf zones encountered however works were completed successfully in Jacksonville, Florida.

Maritech employed its US Subsidiary, Marpro LLC for these works.


2014-A-AMX1_RW-DR

Maritech successfully completed the remedial protection works of the AMX-1 Cable System in the Challenging surf zone of Fortaleza, Brazil. The particular cable system has been prone to exposures due to migrating sediments on the seabed caused by strong surf and current conditions. This led to the Subsea Cable being left un- protected to external threat following its initial burial. Maritech successfully mitigated this threat employing its Dive Supervisors with a Maritech Local Dive Team and Spreads permanently imported in Brazil, to successfully install Articulated Pipes and Rock Clamps to the exposed cable in water depths up to 20m.


2014-T-SCILLY-UK

Maritech successfully completed a complicated 1.5km Direct Shore end including installation of mechanical protection and burial for the Scilly Islands Cable system connecting these remote islands to the UK with a re-cycled Fiber Optic Cable. This complicated project involved first recovering an Out Of Use Cable from the seabed and then relaying it from the UK to the Scilly Islands through a series of reefs and rock outcrops. Many anchoring points and careful planning of pull-in practices were employed to ensure the cable weaved through numerous rock outcrops and ensure it laid within sediment able to bury and protect the cable. Water depths ranged from 0 to 25m and works were completed successfully in St. Mary’s Island, Scilly, UK.
Maritech employed its UK Subsidiary for these works, Maritech UK Ltd while simultaneously working on the Scottish Highlands and Islands projects involving over 40 direct Shore End Subsea Cable Installations in only 3 months over the summer seasson of 2014.


PCCS F.O. Cable System Aruba Seg. 3

Project involved the Direct Shore End Landing through 520m pre-installed duct of Fiber Optic Cable to one landing site (Arashi), Aruba including diver inshore surveys and installation of Articulated Pipes (25m) Cable Protection Systems.
All project equipment and spreads were locally fabricated, tested and deployed with preparations undertaken by Maritech’s personnel. Project was executed safely, effectively and on-time.


2014-A-PCCS-RW-USA

Maritech performed remedial protection works for Alcatel-Lucent, on the PCCS Submarine Fiber optic cable system at Segment 1 Jacksonville shore end. Remedial works included survey using RD-7000 Cable Tracker, articulated pipe installation and re-burial of cable within a challenging surf zone.
Works have been successfully completed in a timely and safely manner.


2014-A-PCCS-USA

Maritech successfully completed a 3km Direct Shore end including Burial with its subsea SKAS Jet Trencher for the new Fiber Optic Cable PCCS connecting USA to the Caribbean. Water depths ranged from 0 to 25m with strong surf zones encountered however works were completed successfully in Jacksonville, Florida.

Maritech employed its US Subsidiary, Marpro LLC for these works.


2014-A-AMX1_RW-DR

Maritech successfully completed the remedial protection works of the AMX-1 Cable System in the Challenging surf zone of Fortaleza, Brazil. The particular cable system has been prone to exposures due to migrating sediments on the seabed caused by strong surf and current conditions. This led to the Subsea Cable being left un- protected to external threat following its initial burial. Maritech successfully mitigated this threat employing its Dive Supervisors with a Maritech Local Dive Team and Spreads permanently imported in Brazil, to successfully install Articulated Pipes and Rock Clamps to the exposed cable in water depths up to 20m.


2014-T-SCILLY-UK

Maritech successfully completed a complicated 1.5km Direct Shore end including installation of mechanical protection and burial for the Scilly Islands Cable system connecting these remote islands to the UK with a re-cycled Fiber Optic Cable. This complicated project involved first recovering an Out Of Use Cable from the seabed and then relaying it from the UK to the Scilly Islands through a series of reefs and rock outcrops. Many anchoring points and careful planning of pull-in practices were employed to ensure the cable weaved through numerous rock outcrops and ensure it laid within sediment able to bury and protect the cable. Water depths ranged from 0 to 25m and works were completed successfully in St. Mary’s Island, Scilly, UK.
Maritech employed its UK Subsidiary for these works, Maritech UK Ltd while simultaneously working on the Scottish Highlands and Islands projects involving over 40 direct Shore End Subsea Cable Installations in only 3 months over the summer seasson of 2014.


PCCS F.O. Cable System Aruba Seg. 3

Project involved the Direct Shore End Landing through 520m pre-installed duct of Fiber Optic Cable to one landing site (Arashi), Aruba including diver inshore surveys and installation of Articulated Pipes (25m) Cable Protection Systems.
All project equipment and spreads were locally fabricated, tested and deployed with preparations undertaken by Maritech’s personnel. Project was executed safely, effectively and on-time.


2014-A-PCCS-RW-USA

Maritech performed remedial protection works for Alcatel-Lucent, on the PCCS Submarine Fiber optic cable system at Segment 1 Jacksonville shore end. Remedial works included survey using RD-7000 Cable Tracker, articulated pipe installation and re-burial of cable within a challenging surf zone.
Works have been successfully completed in a timely and safely manner.


2014-A-PCCS-USA

Maritech successfully completed a 3km Direct Shore end including Burial with its subsea SKAS Jet Trencher for the new Fiber Optic Cable PCCS connecting USA to the Caribbean. Water depths ranged from 0 to 25m with strong surf zones encountered however works were completed successfully in Jacksonville, Florida.

Maritech employed its US Subsidiary, Marpro LLC for these works.


2014-A-AMX1_RW-DR

Maritech successfully completed the remedial protection works of the AMX-1 Cable System in the Challenging surf zone of Fortaleza, Brazil. The particular cable system has been prone to exposures due to migrating sediments on the seabed caused by strong surf and current conditions. This led to the Subsea Cable being left un- protected to external threat following its initial burial. Maritech successfully mitigated this threat employing its Dive Supervisors with a Maritech Local Dive Team and Spreads permanently imported in Brazil, to successfully install Articulated Pipes and Rock Clamps to the exposed cable in water depths up to 20m.


2014-T-SCILLY-UK

Maritech successfully completed a complicated 1.5km Direct Shore end including installation of mechanical protection and burial for the Scilly Islands Cable system connecting these remote islands to the UK with a re-cycled Fiber Optic Cable. This complicated project involved first recovering an Out Of Use Cable from the seabed and then relaying it from the UK to the Scilly Islands through a series of reefs and rock outcrops. Many anchoring points and careful planning of pull-in practices were employed to ensure the cable weaved through numerous rock outcrops and ensure it laid within sediment able to bury and protect the cable. Water depths ranged from 0 to 25m and works were completed successfully in St. Mary’s Island, Scilly, UK.
Maritech employed its UK Subsidiary for these works, Maritech UK Ltd while simultaneously working on the Scottish Highlands and Islands projects involving over 40 direct Shore End Subsea Cable Installations in only 3 months over the summer seasson of 2014.


PCCS F.O. Cable System Aruba Seg. 3

Project involved the Direct Shore End Landing through 520m pre-installed duct of Fiber Optic Cable to one landing site (Arashi), Aruba including diver inshore surveys and installation of Articulated Pipes (25m) Cable Protection Systems.
All project equipment and spreads were locally fabricated, tested and deployed with preparations undertaken by Maritech’s personnel. Project was executed safely, effectively and on-time.


2014-A-PCCS-RW-USA

Maritech performed remedial protection works for Alcatel-Lucent, on the PCCS Submarine Fiber optic cable system at Segment 1 Jacksonville shore end. Remedial works included survey using RD-7000 Cable Tracker, articulated pipe installation and re-burial of cable within a challenging surf zone.
Works have been successfully completed in a timely and safely manner.


2014-A-PCCS-USA

Maritech successfully completed a 3km Direct Shore end including Burial with its subsea SKAS Jet Trencher for the new Fiber Optic Cable PCCS connecting USA to the Caribbean. Water depths ranged from 0 to 25m with strong surf zones encountered however works were completed successfully in Jacksonville, Florida.

Maritech employed its US Subsidiary, Marpro LLC for these works.


2014-A-AMX1_RW-DR

Maritech successfully completed the remedial protection works of the AMX-1 Cable System in the Challenging surf zone of Fortaleza, Brazil. The particular cable system has been prone to exposures due to migrating sediments on the seabed caused by strong surf and current conditions. This led to the Subsea Cable being left un- protected to external threat following its initial burial. Maritech successfully mitigated this threat employing its Dive Supervisors with a Maritech Local Dive Team and Spreads permanently imported in Brazil, to successfully install Articulated Pipes and Rock Clamps to the exposed cable in water depths up to 20m.


2014-T-SCILLY-UK

Maritech successfully completed a complicated 1.5km Direct Shore end including installation of mechanical protection and burial for the Scilly Islands Cable system connecting these remote islands to the UK with a re-cycled Fiber Optic Cable. This complicated project involved first recovering an Out Of Use Cable from the seabed and then relaying it from the UK to the Scilly Islands through a series of reefs and rock outcrops. Many anchoring points and careful planning of pull-in practices were employed to ensure the cable weaved through numerous rock outcrops and ensure it laid within sediment able to bury and protect the cable. Water depths ranged from 0 to 25m and works were completed successfully in St. Mary’s Island, Scilly, UK.
Maritech employed its UK Subsidiary for these works, Maritech UK Ltd while simultaneously working on the Scottish Highlands and Islands projects involving over 40 direct Shore End Subsea Cable Installations in only 3 months over the summer seasson of 2014.


PCCS F.O. Cable System Aruba Seg. 3

Project involved the Direct Shore End Landing through 520m pre-installed duct of Fiber Optic Cable to one landing site (Arashi), Aruba including diver inshore surveys and installation of Articulated Pipes (25m) Cable Protection Systems.
All project equipment and spreads were locally fabricated, tested and deployed with preparations undertaken by Maritech’s personnel. Project was executed safely, effectively and on-time.


2014-A-PCCS-RW-USA

Maritech performed remedial protection works for Alcatel-Lucent, on the PCCS Submarine Fiber optic cable system at Segment 1 Jacksonville shore end. Remedial works included survey using RD-7000 Cable Tracker, articulated pipe installation and re-burial of cable within a challenging surf zone.
Works have been successfully completed in a timely and safely manner.


2014-A-PCCS-USA

Maritech successfully completed a 3km Direct Shore end including Burial with its subsea SKAS Jet Trencher for the new Fiber Optic Cable PCCS connecting USA to the Caribbean. Water depths ranged from 0 to 25m with strong surf zones encountered however works were completed successfully in Jacksonville, Florida.

Maritech employed its US Subsidiary, Marpro LLC for these works.


2014-A-AMX1_RW-DR

Maritech successfully completed the remedial protection works of the AMX-1 Cable System in the Challenging surf zone of Fortaleza, Brazil. The particular cable system has been prone to exposures due to migrating sediments on the seabed caused by strong surf and current conditions. This led to the Subsea Cable being left un- protected to external threat following its initial burial. Maritech successfully mitigated this threat employing its Dive Supervisors with a Maritech Local Dive Team and Spreads permanently imported in Brazil, to successfully install Articulated Pipes and Rock Clamps to the exposed cable in water depths up to 20m.


2014-T-SCILLY-UK

Maritech successfully completed a complicated 1.5km Direct Shore end including installation of mechanical protection and burial for the Scilly Islands Cable system connecting these remote islands to the UK with a re-cycled Fiber Optic Cable. This complicated project involved first recovering an Out Of Use Cable from the seabed and then relaying it from the UK to the Scilly Islands through a series of reefs and rock outcrops. Many anchoring points and careful planning of pull-in practices were employed to ensure the cable weaved through numerous rock outcrops and ensure it laid within sediment able to bury and protect the cable. Water depths ranged from 0 to 25m and works were completed successfully in St. Mary’s Island, Scilly, UK.
Maritech employed its UK Subsidiary for these works, Maritech UK Ltd while simultaneously working on the Scottish Highlands and Islands projects involving over 40 direct Shore End Subsea Cable Installations in only 3 months over the summer seasson of 2014.


Maritech certificates


Postal Address:
PO BOX 70384
166 10 Glyfada
Athens - Greece

Telephone & Fax:
Tel :+30 210 89 56 872
Fax:+30 210 96 70 535

Contact:
Tel: +30 210 9673174
Email: This email address is being protected from spambots. You need JavaScript enabled to view it.